PROD-2026-000003
PROD-2026-000003ERP Production OrderCMPINTERNAL
Native fields
- Item
- ITM-FG-RACK · Metrolane roof rack, assembled
- Plant
- PLT-PUNEPLT-PUNE
- Warehouse
- WH-PUNE · Pune CentralWH-PUNE
- Planned Qty
- 4
- Released Qty
- 4
- Completed Qty
- 2
- Rejected Qty
- 1
- Planned Start Date
- 15 Jul 2026
- Planned End Date
- 15 Jul 2026
- Actual Complete At
- 16 Jul 2026, 13:00 IST
- Cost Center
- CC-PROCCC-PROC
- Execution Ref
- MES-WO-2026-000003
Values as ERP stores them. They are source facts, not canonical facts.
Operational links
MES Work Order
Canonical record
PROD-2026-000003
Production Order · PROD-2026-000003
The canonical business record projected from this source record.
Related records
Material Issues (1) · via production_order_id
- MI-2026-000004 · PST
Production Receipts (1) · via production_order_id
- PREC-2026-000002 · PST
Related within ERP
Components
2| Line No. | Item | Required Qty | Issued Qty | Returned Qty |
|---|---|---|---|---|
| 1 | ITM-PACK-BOLT · M8 mounting bolt set | 8 | 0 | 0 |
| 2 | ITM-COMP-CLAMP · Rack end clamp | 4.2 | 6 | 0 |
erp_production_component rows, as ERP stores them
Operations
3| Operation Seq | Work Center | Status | Qty Completed |
|---|---|---|---|
| 10 | WC-ASSYWC-ASSY | PLN | 0 |
| 20 | WC-ASSYWC-ASSY | PLN | 0 |
| 30 | WC-ASSYWC-ASSY | PLN | 0 |
erp_production_operation rows, as ERP stores them